Ahmed N.
AN
Project Planning Engineer at PRINCIPAL BUILDERS - Engineers & Contractors

After scheduling a baseline of any project in P6, we oftenly export cash flow. My question is, what date does P6 take as cutt off date for monthly cash flow for your project.

If time span of project is 12 months, P6 will give you a cumulative cash flow till 12th month. What date of the month does P6 take as a cutoff date when we draw S-Curve. Actually when I draw it manually in excel it gives different values and when I schedule P6 for my monthly reports it give different values. Forexample: if you schedule P6 for 3rd month schedule % is 15.52% and when I check it from activity usage profile it is giving the value of 16.21%.
1 comment
Looks like you’re not logged in.
Users need to be logged in to answer questions
Log In
Elshad H.
EH
Planning Engineer at Subsea 7
0
Cut off date for monthly is up to the organization. Generally last friday or Thursday of the month is the cut off