Project Planning Engineer at PRINCIPAL BUILDERS - Engineers & Contractors
After scheduling a baseline of any project in P6, we oftenly export cash flow. My question is, what date does P6 take as cutt off date for monthly cash flow for your project.
If time span of project is 12 months, P6 will give you a cumulative cash flow till 12th month. What date of the month does P6 take as a cutoff date when we draw S-Curve. Actually when I draw it manually in excel it gives different values and when I schedule P6 for my monthly reports it give different values.
Forexample: if you schedule P6 for 3rd month schedule % is 15.52% and when I check it from activity usage profile it is giving the value of 16.21%.
For more than 30 years, successful projects around the world have relied on Oracle Construction and Engineering's Primavera solutions to plan, build, and operate critical assets. It is the only solut
With over 2.5 million reviews, we can provide the specific details that help you make an informed software buying decision for your business. Finding the right product is important, let us help.